Tuesday, July 23, 2019

Release Procedure for PR With classification In Sap MM CREATION OF CHARACTERISTIC

Materials Management / Purchasing/ Purchase Requisition / Release Procedure /

Procedure with Classification/ Edit Characteristics.



Enter characteristic name (ceban_gswrt ) and click on create button.


Release Procedure for PR With classification


Now click on additional data tab

table name : ceban

Field name : gswrt & press enter


Capture


In basic data tab enter

Currency : inr &

check multiple values & interval vals allowed as shown below


Capture







Now click on values tab & enter as below


Capture


Now click on restrictions tab

Enter class type : 032 & press enter, below screen appears


Capture


Now Click on save button below screen appears.


Capture




CREATION OF CLASSES



Materials Management / Purchasing/ Purchase Requisition / Release Procedure / Procedure with Classification/ Edit Classes.


Enter class, class type, & click on create button.


Capture


Enter description


Capture


now click on char. tab

& enter characteristic name, & press enter, & save it.


Capture




Set Up Procedure with Classification



Materials Management / Purchasing/ Purchase Requisition / Release Procedure / Procedure with Classification/ set up procedure with classification


Now click on release groups


Capture


Click on new entriesa

Enter rel.grp, class, description & click on save


Capture


Press f3, f3(back) & click on release codes


Capture







Click on new entries & enter grp, code, desc as below

Now press enter & click save button.


Capture


Press f3, f3(back) & click on release indicators


Capture


Click on new entries

Enter release id, changeabile, value change & press save button.


Capture


Similarly create another release id as shown below. & save it , press f3 ,f3.


Capture

Now click on release strategies.


Capture


Now click on new entries

Enter release grp, release strategy, & release codes as below.


Capture


Now click on release prerequisites. Check od check box & click on continue.


Capture


Now click on release statuses


Capture


Observe the below screen and click on continue


Capture


Now save it & click on classification


Capture


Follow below steps

Check >=5000,00 inr check box & press enter


Capture


Capture


Now press f3.

Click on release simulation.


Capture


Following screen appears & click on simulate release to do release test


Capture


Now click on release possible then only OD can release pr.


Capture


Now press f3 following screen appears.


Capture


Simillarly create release strategies with A3,A2,A1 in GI Group with these conditions

A3 = < 5000 & approval should be by plant manager A

A2 = >=10000 & approval should be by stock controller A & plant manager A

A1 = <10000 & approval should be by stock controller A.

Now create pur.req & we can release this pur.req itemwise.







Creation of purchase requisition



Now create pur.req t.code- ME51N


Capture


Enter material , plant, delivery date, quantity & press enter button.


Capture


Now press check button below screen appears


Capture


Press Save .


Capture




Release procedure for pur,req t.code-ME54N



Observe the release strategy tab .


Capture


Click on release options in release strategy tab. Now SA is released


Capture


Click on release options in release strategy tab again to release PA as shown below.


Capture


Capture


Click on save button.


Capture